Phan Thiet - Dau Giay Expressway graduately disclosure, progress guarantee

The Phan Thiet - Dau Giay expressway still ensures the construction progress, as noted at the construction site in early September.

Mr. Nguyen Doan Tan - Project CEO said that by the end of August, construction and installation bidding packages had reached 83.78% of the plan of 2021 and disbursed 1,532 billion VND. In the near future, the Phan Thiet - Dau Giay expressway project will continue to work on the K95, K98 roads, spread crushed stone, completion of all horizontal culverts and underpasses.